last sunday, we had a site visit... actually the actual date for us to do the installation is on week 5 but since there is certain reason we need to bring forward the date...
DAY 1 : 26/4/10 (travelling day)
DAY 2 : 27/4/109.30 - breakfast
10.00 - drive to the site (pole 102, 90, 88)
10.40 - reset Current Transformer / energy logger (at site)
11.15 - install energy logger at straight trough joint (on the tray at the top of pole)
complete installation for the 1st day
those two pictures above are taken during the installation process..according to En. Saeidin, this work are done 7m from the land. the person who is responsible to do this must know the theory behind it as well, its not simply go up there and plug in the device. ie; the person should now the basic idea about eletcric. however, this activity was supervised by the TNBR's foreman from cable unit.
Day by day, new thing pop up...for today after uninstall the energy logger, we have to transfer the collected data into the software in order for us to see the patern of current flow during peak hour and ordinary hour.
the lady in blue jacket was my sub-supevisor...she was one of the engineer in High Voltage Diagnostic unit...at this moment we all quite stress when the data we get not as what we expected...discussion still ongoing eventhough we sat next to the main road...
"Poning Eden ngan data nie" <<< en. saeidin ^_^
dangerous just next to me... " malang tak berbau "...
communicate with teamate up there...
Praise to God... we have a good coorperation with them in order for us to use the crane hogger...wothout their help, for sure we cannot reach the top pole
the cable on the tray was the joint cable and the energy logger was installed here..
WRONG!!!!
the cable shoudn't be hang up just like that...every single joint MUST place on the tray